Ministerial Order determining the List of Works, Activities and Projects subject to an Environmental Impact Assessment


Rwanda

Ministerial Order determining the List of Works, Activities and Projects subject to an Environmental Impact Assessment

Ministerial Order 1 of 2018

The Minister of Environment;Pursuant to the Constitution of the Republic of Rwanda of 2003 revised in 2015, especially in Articles 121, 122 and 176;Pursuant to Organic Law n° 04/2005 of 08/04/2005 determining the modalities of protection, conservation and promotion of environment in Rwanda, especially in Articles 67 and 70;Having reviewed Ministerial Order n° 004/2008 of 15/08/2008 establishing the list of works, activities and projects that have to undertake an environment impact assessment;After consideration and approval by the Cabinet, in its session of 11/04/2018;ORDERS:

Article One – Purpose of this Order

This Order determines the list of works, activities and projects subject to an environmental impact assessment before being granted authorisation to commence.

Article 2 – Definitions

In this Order, the following terms have the following meanings:full environmental impact assessment: an environmental impact study that covers all the steps of environmental impact assessment process;partial environmental impact assessment: an environmental impact study limited to identification of environmental issues and appropriate mitigation measures.

Article 3 – List of works, activities and projects subject to a full environmental impact assessment

The list of works, activities and projects that have to be subject to a full environmental impact assessment before being granted authorisation to commence is in annex I of this Order.

Article 4 – List of works, activities and projects subject to a partial environmental impact assessment

The list of works, activities and projects that have to be subject to a partial environmental impact assessment before being granted authorisation to commence is in annex II of this Order.Those works, activities and projects are subjected to screening for environmental clearance.

Article 5 – Works, activities and projects that are not on the list

When it is necessary and evident that a work, activity or a project, not listed on the annex to this Order, may have a negative impact on the environment, Rwanda Environment Management Authority or any other person given a written authorization by that Authority may request the owner to conduct an environmental impact assessment.

Article 6 – Repealing provision

Ministerial Order n° 004/2008 of 15/08/2008 establishing the list of works, activities and projects that have to undertake an environment impact assessment and all other prior provisions contrary to this Order are repealed.

Article 7 – Commencement

This Order comes into force on the date of its publication in the Official Gazette of the Republic of Rwanda.

Annex I

Works, activities and projects subject to a full environmental impact assessment are the following:

all buildings classified in the following categories:a)entertainment and public assembly facilities;b)theater and indoor sport facilities;c)places of worship;d)outdoor sport facilities;e)learning/training institutions that include any building or a group of buildings under single management that are used for more than five hundred (500) students or trainees;f)hospitals and health centers;g)publicly accessible facilities with a capacity to host more than five hundred (500) people;industries;buildings with activities which can cause hazards;warehouses for storage of hazardous materials;warehouses and storage facilities of perishable agricultural commodities occupying an area of a half a hectare (½ ha) and above;places where people are detained for punitive or corrective reasons or because of their mental condition;places of non-industrial commercial activities, where such activities or commercial products may cause fire, cause combustion with extreme rapidity, give rise to poisonous fumes or cause explosions;garages;bonded warehouse;10°hotels;11°construction and repair of international, national, District roads and repair of large bridges;12°construction of hydro-dams, hydropower plants and electrical lines of high and medium voltage;13°construction of petroleum products and gas pipelines and their storage tanks;14°construction of terminal ports, airports and railways;15°agricultural and breeding activities which use chemical fertilizers and pesticides in wetlands;16°large scale investment projects in agricultural and breeding activities which use chemical fertilizers and pesticides on hill sides;17°works and activities that involve genetic modification of seeds and animals;18°works in parks and in its buffer zone;19°all works related to mining;20°commercial small and large scale quarrying;21°construction of artificial lakes;22°construction of water storage dams;23°works or activities for marshlands reclamation;24°construction of slaughter houses.

Annex II

Works, activities and projects subject to a partial environmental impact assessment are the following:

towers and antennas;all types of buildings, except those qualified for full environmental impact assessment, with a capacity to host more than one hundred (100) people but not exceeding five hundred (500) people;micro hydroelectric power, low voltage electric lines and off grid electrical lines.